  • Q87. Where shall the fire pump be located in a building?

    Sunday,2 Aug 2015

    A87.   Fire Pumps shall be located at the ground floor or Fire Access level at the lowest level of the building, pumping water upwards. Fire pumps at levels higher than the lowest level of the building with water supply feeding downwards is not allowed.

    Hits :  1021
  • Q88. What shall be height limitation of a building for a mechanical floor to house the transfer fire pump and tank?

    Sunday,2 Aug 2015

    A88.  Any building higher than 90 m in habitable height from the lowest level of the building shall require a transfer pump set and a transfer water tank located on the mechanical floor.

    Hits :  807
  • Q89. What is defined as light hazard occupancies?

    Sunday,2 Aug 2015

    A89.  The areas and occupancies which are used for non-industrial uses and contains low quantity and less combustible materials which are expected to release less heat release rates during fire condition shall be classified as light hazard occupancies.  

    Hits :  938
  • Q90. What is defined as ordinary hazard occupancies?

    Sunday,2 Aug 2015

    A90.  The areas and occupancies used for processing and handling of mainly ordinary combustible materials unlikely to develop intensely burning fires in the initial stages shall be classified as ordinary hazard occupancies.

    Hits :  790
  • Q91. What is defined as ordinary hazard group 1?

    Sunday,2 Aug 2015

    A91.   The areas and occupancies which are used for commercial & industrial uses and contains medium quantity and moderate combustible materials and the storages up to 2.4 meters which are expected to release moderate heat release rates during fire condition shall be classified as Ordinary Hazard group-1. 

    Hits :  820
  • Q92. What is defined as ordinary hazard group 2?

    Sunday,2 Aug 2015

    A92.  The areas and occupancies which are used for commercial & industrial uses and contain medium quantity and moderate to high combustible materials and the storages up to 3.6 mtrs which are expected to release moderate heat release rates and the storages up to 2.4 mtrs which are high heat release rates during fire condition shall be classified as Ordinary Hazard group-2.  

    Hits :  586
  • Q93. What is defined as extra high hazard group 1?

    Sunday,2 Aug 2015

    A93.   The areas and occupancies which are used for industrial uses and contains high quantity and very high combustible materials which will support fast development of fire and are expected to release very high heat release rates during fire condition and having less or no combustible or flammable liquids & gases shall be classified as Extra high hazard group-1.

    Hits :  500
  • Q94. What is defined as extra high hazard group 2?

    Sunday,2 Aug 2015

    A94.  The areas and occupancies which are used for industrial uses and contain moderate to high quantity of flammable & combustible liquids and gases which will support rapid growth of fire and expected to release very high heat release rates during fire condition shall be classified as Extra High hazard group-2.

    Hits :  457
  • Q95. What is the temperature and fire rating of smoke exhaust or extract fans?

    Sunday,2 Aug 2015

    A95.     Smoke Exhaust or extract fans shall be capable of operating effectively at 400°C for 2 hours.

    Hits :  953
  • Q96. What is the minimum distance between air intakes and any exhaust discharge openings?

    Sunday,2 Aug 2015

    A96.  Openings for the intakes of outdoor air to all air handling systems, mechanical ventilation systems, pressurization systems of exit staircases and internal corridors, and smoke control systems shall be no less than 5m from any exhaust discharge openings.

    Hits :  921
  • Q97. When can a concealed space between ceiling and roof or raised floors be used as air plenum?

    Sunday,2 Aug 2015

    A97.     A concealed space between the ceiling and floor above it, ceiling and roof, or raised floor and structural floor of a building may be used as a plenum provided that the concealed space contains only:

    i.    Mineral-insulated metal-sheathed cable,  
    ii.    Aluminum-sheathed cable,  
    iii.    Copper-sheathed cable,  iv.     Rigid metal conduit,  
    v.    Enclosed metal trunking,  
    vi.    Flexible metal conduit,  
    vii.    Liquid-tight flexible metal conduit in lengths not more than 2 m, or metal-clad cables; viii.     Communication cables for computers, television, telephone and intercommunication system;
    ix.    Fire protection installations;
    x.    Pipes of non-combustible material conveying non-flammable liquids

    Hits :  232
  • Q98. What is the fire rating of dampers to be installed in ducts penetrating fire walls?

    Sunday,2 Aug 2015

    A98.   Duct penetrations of fire walls should be avoided. Approved fire dampers shall be provided where air ducts penetrate or terminate at openings in walls or partitions required to have a fire resistance rating of 1 hour or more depending on the fire rating of the wall.

    Hits :  989
  • Q99. In which application a fire damper is not required?

    Sunday,2 Aug 2015

    A99.     A fire damper shall not be required for the following:

    1. Clothes Dryer Exhaust Ducts
    2. Hazardous Fume Exhaust Duct
    3. Stairwell Pressurization Ducts iv. Smoke Extraction Ducts
    4. Laundry and Trash Chutes
    Hits :  1114
  • Q100. What is the type of approved material to be used for the construction of ceiling plenum?

    Sunday,2 Aug 2015

    A100. Materials used in the construction of a ceiling plenum shall be noncombustible or shall be limited combustible having a flame spread index of not more than 25 and a maximum smoke developed index of 50.

    Hits :  492
  • Q101. In what situation does staircases serving the basement level need to be pressurized?

    Sunday,2 Aug 2015

    A101. All fire exit staircases that serve the basement floors shall also be pressurized if the same staircase shafts serving the upper floors are pressurized. Fire exit staircases that only serve the basement which have more than 2 levels or more than 7m below the level of discharge (high depth underground buildings and structures) shall be pressurized. Fire exit staircases that only serve the basement which have less than 2 or levels or less than 7m below the level of discharge (low depth underground buildings and structures) shall be provided with mechanical ventilation.

    Hits :  608
  • Q102. At what height shall a building have its exit staircases pressurized?

    Sunday,2 Aug 2015

    A102. In any building of which the habitable height exceeds 23 m, any internal exit staircases without adequate provision for natural ventilation shall be pressurized.

    Hits :  1059
  • Q103. What is the arrangement for multiple injections for staircase pressurization?

    Sunday,2 Aug 2015

    A103. A single-point injection system shall not be used where the stairwell height is more than eight stories. Stairwells more than 3 storeys above grade or 15m in height, which ever lower shall be provided with multiple-injection systems.

    Hits :  724
  • Q104. What is the minimum rate of mechanical ventilation for internal corridors?

    Sunday,2 Aug 2015

    A104. Mechanically ventilated internal corridor shall have a purging rate of at least 6 air changes per hour.

    Hits :  856
  • Q105. What is the minimum rate of mechanical ventilation for basements?

    Sunday,2 Aug 2015

    A105. The purge rate for basement shall be at least 9 air changes per hour.

    Hits :  849
  • Q106. What is the minimum clear height for the smoke layer when designing smoke management systems?

    Sunday,2 Aug 2015

    A106. The design smoke layer base shall be above the heads of people escaping beneath it. The minimum height shall be 1830mm

    Hits :  1003

DCD Measures

CONTACT US CONTACT US

Contact Us

x
997
+971 800 997
+971 4 7052041 - 24/7
customer.care@dcd.gov.ae & info@dcd.gov.ae
Arc, P.O. Box 11377 Dubai, UAE
Contact center receives your call 24 X 7 X 365

NEWSLETTER Newsletter

Page last updated 10.06.2024

Site is best viewed in a 1280x1024 screen resolution.

Dubai Smart Government DCD Paperless Government official website اسعاد Dubai Careers

Visitors Counter

577577563
Today
Yesterday
This Week
Last Week
This Month
Last Month
All days
11031
80858
382603
37756998
721147
2468726
577577563
Your IP: 10.234.102.113
2025-05-09 08:49
  1. Download DCD Smart App
  2. Android App Ios App
 

Application Status

Application Status

smile meter icon dcd
esuggest icon dcd en

123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890123456789 123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890123456789 123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890123456789 123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890123456789 123456789012345678901234567890123456789012345678901234567890123456789012345678901234567890123456789 123456789 123456

Please Click Here to Listen Highlighted Text

Still need help ?

We are here to provide you with any information or answer any questions you may have

You may also find your answer in our FAQs section